The Colorado Department of Transportation in 1996 initiated its High-Priority Projects plan, a set of 28 projects across the state which CDOT committed to completing over the next approximately 25 years. The projects range from interchange reconstruction to major widening to resurfacing.
In 1999,
a wrinkle was thrown in: Governor Bill Owens, elected in 1998,
spearheaded an effort to speed up the projects through bonding large
amounts of money. The legislature placed on the November 1999 ballot
Referendum A, also known as the TRANs Measure. TRANs stands for
Transportation Revenue Anticipation Notes, and allows the State of
Colorado to issue bonds backed against future federal gas tax
revenue, for the purpose of speeding up the projects. The measure
passed with about 65% voting in favor of it.
TRANs are bonds which give the Colorado Department of Transportation a large influx of money now, and allow it to speed up many projects that would otherwise take longer to complete as the money slowly rolled in. The bond issue totaled $1.7 billion, while the total payback with interest will be at or below $2.3B. The bonds will be paid back gradually with federal gas tax money (18¢ a gallon) that is allocated to the state every year, along with state gas tax revenue. Taxes were not increased.
By issuing the bonds now and getting a large amount of cash upfront, CDOT is able to build many projects sooner. Since the interest rate on the bonds (probably 4% to 6%) will very likely be below the inflation of construction costs (probably 7% to 9%), money will be saved. The projects can be completed faster, thus tying up roadways with construction for a shorter period of time.
The reason this measure was on the ballot is because of Colorado's TABOR constitutional amendment. The "Taxpayer's Bill of Rights" forbids the state to go into debt without voter approval. When legislation was first introduced in early 1999 to implement TRANs, both the legislature and the Attorney General's office concluded TRANs were not truly debt, and would not need voter approval. However, the issue was brought before the state Supreme Court, which ruled TRANs did indeed constitute debt. Thus, the issue was put on the ballot for voter approval.
While the Bill Owens administration likes to take credit for speeding up the High-Priority Projects, it is the Roy Romer administration and the Colorado Transportation Commission which get credit for first identifying the 28 projects in 1996.
|
Not yet completed |
Nearing completion |
Completed |
|
Current tally:
|
||
Project |
1999 Cost |
Status |
Impact of TRANs Bonds |
|
|
Not set |
Project not yet set |
Unknown |
Powers BoulevardColorado Springs New freeway |
$220M |
• Some stages built as expressway to be converted to
freeway at later date. • Platte/Powers interchange completed November 2001 • Research to Briargate completed June 2005 • Briargate to SH 83 completed September 2005 • Powers/Woodmen interchange under construction |
Accelerated by 2 years to possible 2012 completion date |
|
|
$69.7M |
Completed September 2002 |
None |
|
|
$342.3M |
Completed December 2007 |
Accelerated by 1 year |
|
|
$365M |
• SH 105 interchange reconstruction: completed 2004 • Widening Wolfensberger to Founders: completed November 2007 • Founders/Meadows: completed 1998 • Widening to 6 lanes Founders to Lincoln: completed 2002 • Widening to 8 lanes Founders to Lincoln: at future date • Other stages at future date |
Possibly accelerated to 2018 completion date |
|
|
$593.6M |
T-REX project. Roadway improvements completed August 2006. Light rail open November 2006. |
Accelerated by 11 years |
|
|
$97.5M |
Completed December 2003 |
None |
|
|
$146.5M |
• WB I-270 connection: Completed 2000 |
Was accelerated by 1 year to 2005 completion date, but recession halted funding for final phase |
|
|
$81.5M |
• SH 7 to SH 52: Completed 2004 |
Accelerated by 3 years |
|
|
$302.7M |
Possible 2022 completion date |
Unknown |
|
|
- |
Completed 1999 |
N/A. Completed prior to TRANs bonding |
|
|
- |
Completed 1998 |
N/A. Completed prior to TRANs bonding |
|
|
$74.8M |
Completed November 2006 |
Accelerated by 2 years |
|
|
$72.2M |
Completed October 2004 |
Accelerated by 8 years |
|
|
$1.1B |
Project not yet set |
Unknown |
|
|
Not set |
Project not yet set |
Unknown |
|
|
$121.6M |
Completed October 2002 |
Accelerated by 5 years |
|
|
$45.5M |
Completed August 2002 |
Accelerated by 4 years |
|
|
$185.9M |
Completed November 2004 |
Accelerated by 1 year |
|
|
- |
Completed pre-1998 |
N/A. Completed prior to TRANs bonding |
|
|
$60.1M |
• US 550 to SH 172 under construction |
Accelerated by 2 years |
|
|
$68.4M |
• Numerous stages completed 1990s-2004 |
Accelerated by 2 years to 2007 completion date |
|
|
$85.4M |
Completed October 2002 |
Accelerated by 8 years |
|
|
$63.1M |
Completed November 2002 |
Accelerated by 6 years |
|
|
$184.3M |
Scheduled completion 2010 |
Accelerated by 3 years |
|
|
$92.4M |
Completed August 2006 |
Was on track to finish 1 year ahead of schedule, but soil problems on the Berthoud bypass caused delays |
|
|
- |
Completed August 2000 |
N/A. Completed prior to TRANs bonding |
|
|
$48.8M |
Possible 2007 completion date |
None |
Project |
1999 Cost |
Status |
Impact of TRANs Bonds |
Continue:
Last updated 23 February 2008